The Latvian Investment and Development Agency has announced a tender for the development of a technical concept for the ELWIND offshore wind farm. The project preparation process will consist of two phases – Pre-FEED and FEED.
The Pre-FEED or preliminary study phase will focus on developing a general technical concept using publicly available information to update the project’s baseline scenario. This will include an assessment of the site conditions and possible electricity connection options, which will serve as a basis for further development.
The FEED phase will summarize the results obtained so far from the power grid connection study, environmental impact assessment, site data, and the Pre-FEED phase. It will identify the necessary changes and determine additional studies to ensure the continuation of the project.
Pre-FEED is expected to be completed within four months, with FEED work commencing a month later. The total contract duration is 36 months. The deadline for submitting bids is 11:00 a.m. (EET) on 8 September 2025. More detailed information is available on the Latvian Electronic Procurement System, identification number LIAA 2025/90.
Source: ELWIND OFFSHORE, 08.08.2025.